Bond Projects Update

The last project of the 2016 Bond is underway! Check back here every two weeks for updates on the status of the project!

Projects Status Report
May 12, 2021
Sports Facilities and Drainage Improvements

  • Contractor has demolished and removed baseball and softball field complex.
  • Mason is laying concrete block at concession/restroom building and approximately 70% complete.
  • Mason is currently laying interior block walls at restrooms.
  • Mason has completed laying concrete blocks at home ticket booth and will be working on masonry facing at existing ticket booths.
  • Contractor has erected gateway arch and will be laying out new concrete walks next week.
  • Charlie expects to have well driller onsite next week.
  • Site contractor is working on installation of sanitary sewer line to McMullen Lane.
  • Lamarr Womack Architects, APISD, and Weaver and Jacobs will be coordinating upcoming work with Texas Multi-Chem.
  • Contractor is installing box culverts between baseball field and new concession/restroom building. They are currently 70% complete.
  • Weaver and Jacobs are expected to start installing roof framing next week.
  • Track has been closed so that contractor can install area drains inside football field.
  • We have an onsite construction meeting scheduled for Wednesday May 26th.
  • Currently this project is on schedule.
construction update 1construction update 2construction update 3construction update 4

Previous Construction Updates

Website by SchoolMessenger Presence. © 2021 Intrado Corporation. All rights reserved.