Bond Projects Update

The Bond Construction Projects are getting closer to completion! Check back here every two weeks for updates on the status of the projects!

Projects Status Report
May 14, 2019

New Elementary School

  • Contractor is is complete with paint first coat on first floor and complete with first coat on second floor.
  • Contractor is 95% complete with entry tower paint.
  • Contractor has started floor prep in classrooms and VCT will be starting this week.
  • Contractor to start installing interior doors and hardware next week.
  • The room signs are in the submittal process.
  • Painter has started exterior tiltwall painting.
  • Contractor to start on exterior drives and parking once site is dry.
  • Krueger has started installing ceiling tile and is 10% complete.
  • Plumber has installed all fixtures and is working on trim out.
  • Electrician has installed 95% of all lighting and switches.
  • Mechanical contractor has installed majority of all ceiling and wall grilles throughout.
  • Manufactured casework has been installed in all classrooms and library furniture is scheduled for delivery this month.
  • All data cabling has been installed and is being terminated in MDF. Internet switch over to new MDF is scheduled for May 31st.
  • LWA office is reviewing landscape plans.
  • Demolition contractor to start mid-June.
Elementary EntranceCafeteriaStairsLibraryGym EntranceGym InteriorGym LobbyGym Restroom

Projects Status Report
May 14, 2019

New Gym Complex

  • Contractor is is installing main entry canopy and is approximately 90% complete. Contractor to form and pour concrete columns next week.
  • Contractor is painting gymnasium walls and is approximately 98% complete.
  • Contractor is painting lobby and restrooms and is approximately 98% complete.
  • Painter to start wall graphics in gym this week.
  • Contractor to start tile floor and walls in showers next week.
  • Plumber has installed all fixtures.
  • Contractor has installed overhead concession doors.
  • Contractor ready to install toilet partitions once floor stain is selected.
  • Contractor to start ceiling grid and tile installation next week.
  • Contractor to start VCT floor in lobby once ceiling is installed.
  • Contractor working on site grading and remainder of sidewalks and exterior lighting.

Video Rendering of New Elementary School Interior



Video Rendering flyby of New Elementary School



Video Rendering of Sports Complex Interior


To view past updates, click HERE.

Website by SchoolMessenger Presence. © 2019 West Corporation. All rights reserved.